poj 1949 Chores
2016-09-17 15:43
232 查看
Description
Farmer John’s family pitches in with the chores during milking, doing all the chores as quickly as possible. At FJ’s house, some chores cannot be started until others have been completed, e.g., it is impossible to wash the cows until they are in the stalls.
Farmer John has a list of N (3 <= N <= 10,000) chores that must be completed. Each chore requires an integer time (1 <= length of time <= 100) to complete and there may be other chores that must be completed before this chore is started. We will call these prerequisite chores. At least one chore has no prerequisite: the very first one, number 1. Farmer John’s list of chores is nicely ordered, and chore K (K > 1) can have only chores 1,.K-1 as prerequisites. Write a program that reads a list of chores from 1 to N with associated times and all perquisite chores. Now calculate the shortest time it will take to complete all N chores. Of course, chores that do not depend on each other can be performed simultaneously.
Input
Line 1: One integer, N
Lines 2..N+1: N lines, each with several space-separated integers. Line 2 contains chore 1; line 3 contains chore 2, and so on. Each line contains the length of time to complete the chore, the number of the prerequisites, Pi, (0 <= Pi <= 100), and the Pi prerequisites (range 1..N, of course).
Output
A single line with an integer which is the least amount of time required to perform all the chores.
Sample Input
7
5 0
1 1 1
3 1 2
6 1 1
1 2 2 4
8 2 2 4
4 3 3 5 6
Sample Output
23
Hint
Here is one task schedule:
Source
USACO 2002 February
Powered By Saruka.
Copyright © 2016 All Rights Reserved.
Farmer John’s family pitches in with the chores during milking, doing all the chores as quickly as possible. At FJ’s house, some chores cannot be started until others have been completed, e.g., it is impossible to wash the cows until they are in the stalls.
Farmer John has a list of N (3 <= N <= 10,000) chores that must be completed. Each chore requires an integer time (1 <= length of time <= 100) to complete and there may be other chores that must be completed before this chore is started. We will call these prerequisite chores. At least one chore has no prerequisite: the very first one, number 1. Farmer John’s list of chores is nicely ordered, and chore K (K > 1) can have only chores 1,.K-1 as prerequisites. Write a program that reads a list of chores from 1 to N with associated times and all perquisite chores. Now calculate the shortest time it will take to complete all N chores. Of course, chores that do not depend on each other can be performed simultaneously.
Input
Line 1: One integer, N
Lines 2..N+1: N lines, each with several space-separated integers. Line 2 contains chore 1; line 3 contains chore 2, and so on. Each line contains the length of time to complete the chore, the number of the prerequisites, Pi, (0 <= Pi <= 100), and the Pi prerequisites (range 1..N, of course).
Output
A single line with an integer which is the least amount of time required to perform all the chores.
Sample Input
7
5 0
1 1 1
3 1 2
6 1 1
1 2 2 4
8 2 2 4
4 3 3 5 6
Sample Output
23
Hint
Here is one task schedule:
Chore 1 starts at time 0, ends at time 5. Chore 2 starts at time 5, ends at time 6. Chore 3 starts at time 6, ends at time 9. Chore 4 starts at time 5, ends at time 11. Chore 5 starts at time 11, ends at time 12. Chore 6 starts at time 11, ends at time 19. Chore 7 starts at time 19, ends at time 23.
Source
USACO 2002 February
/* Problem: 1949 User: saruka Memory: 464K Time: 391MS Language: G++ Result: Accepted */ #include<cstdio> #include<cstring> using namespace std; const int maxn = 20005; int m, n, i, j, k, t, max; int dp[maxn], s; //dp[i]表示干完i杂活所需要的时间 int main() { scanf("%d", &t); s = -1; memset(dp, 0, sizeof(dp)); for(i = 1; i <= t; i++) { max = 0; scanf("%d%d", &m, &n); for(j = 1; j <= n; j++) { scanf("%d", &k); if(dp[k] > max) max = dp[k]; } dp[i] = max + m; if(dp[i] > s) s = dp[i]; } printf("%d\n", s); return 0; }
Powered By Saruka.
Copyright © 2016 All Rights Reserved.
相关文章推荐
- poj 1949——Chores
- POJ 1949 Chores 动态规划
- POJ 1949 Chores
- POJ 1949 Chores
- POJ 1949 Chores(树状DP)
- POJ 1949 Chores(DP)
- POJ 1949 Chores
- poj 1949 Chores 最长路
- POJ 1949 Chores 拓扑排序
- POJ 1949 Chores (DP+拓扑)
- poj 1949 Chores
- 【poj 1949】Chores
- POJ 1949 Chores(树形dp)
- poj 1949 Chores(基础题)
- POJ 1949 Chores
- (POJ DP1.1)POJ 1949 Chores(简单DP)
- POJ 1949 Chores
- [poj 1949]Chores 题解 [dp]
- poj 1949 Chores
- poj 1949 Chores