1.You provide a project cost estimate to the project sponsor. He is unhappy with the estimate, because he thinks the price should be lower. He asks you to cut 15 percent off the project estimate. What should you do?
A. Start the project and constantly look for cost savings.

B. Tell all the team members to cut 15 percent from their estimates.

C. Inform the sponsor of the activities to be cut.

D. Add additional resources with low hourly rates.

你提供了成本估算给项目出资人,他对估算很不满,因为他想到的价格比较低。他要求你消减15%的项目估算。你应该做什么?

A.开始项目,持续节省成本

B.告诉所有的团队成员从他们的估算中消减15%

C.告诉出资人需要消减活动

D.使用较低的工时费率增加额外的资源

C

解释:假设你做的估算是客观的,那么只有砍掉活动(范围),才能降低估算。(2009-6-16 14:10:55)


2. The difference between the cost baseline and the cost budget can be BEST described as?
A. The management reserve

B. The contingency reserve

C. The project cost estimate

D. The cost account

介于成本基准和成本预算之问的费用被称为:

A.管理储备

B.应急储备

C.项目成本估算

D.成本账户

A

解释:管理储备不是项目基准一部分,但包含在项目总预算中。参考:PMBOK2008 P177。(2009-6-16 14:10:55)


3. You are a project manager for a large consulting firm. Your superior has just asked for your input on a decision about which project your company should pursue. Project A has an internal rate of return (IRR) of 12 percent. Project B has a predicted benefit cost ratio (BCR) of 1.3. Project C has an opportunity cost of U.S. $75,000. Project D has a payback period of six months. If you had to choose based on this data, which project would you select?
A. Project A

B. Project B

C. Project C

D. Project D

你是某个大型咨询公司的项目经理。你的上级要求你为公司选择哪个项目做决策提供依据。项目A的内部收益率(IRR)是12%;项目B的标准收益成本分析是1.3;项目C的机会成本是75,000美元;项目D回收期6个月。如果你基于这些数据来选择。你会选择哪个项目?

A.项目A

B.项目B

C.项目C

D.项目D

A

解释:项目C和D无法判断收益;项目A和B对比,内部收益率是计算的纯利润;BCR是收入比成本。(2009-6-16 14:10:55)


4. Although the stakeholders thought there was enough money in the budget,halfway through the project the cost performance index (CPI) is 0.7. To determine the root cause, several stakeholders audit the project and discover the project cost budget was estimated analogously. Although the activity estimates add up to the project estimate, the stakeholders think something was missing in how the "estimate was completed. Which of the following describes what was missing?
A. Estimated costs should be used to measure CPI.

B. SPI should be used, not CPI.

C. Bottom-up estimating should have been used.

D. Past history was not taken into account.

尽管项目干系人认为有足够的预算,项目一半的时候,成本绩效指数是O-7。为了确定核心原因,几个干系人审计项目,发现项目成本预算使用的是类比估算。尽管活动估算累加获得项目估算,项目干系人考虑在估算完成时有些活动被缺失。下列哪个描述了缺失了什么?

A.估算成本应该使用测量CPI

B.SPI应该被使用,而不是CPI

C.白下而上估算应该被使用

D.过去的历史不需要被计算

C

解释:类比估算基于经验,不准确,自下而上估算可以避免遗漏活动的费用预算。参考:PMBOK2008 P172。(2009-6-16 14:10:55)


5. To accommodate a new project in your department, you need to move resources from one project to another. Because your department is currently working at capacity, moving resources will inevitably delay the project from which you move the resources. It would cause the LEAST negative impact if you move resources from which of the following projects?
A, Project A with a benefit cost ratio of 0.8, no project charter, and four resources

B. Project B with a net present value of U.S. $60, 000, 12 resources, and variable costs between U.S. $1,000 and U.S. $2,000 per month

C. Project C with an opportunity cost of U.S. $300,000, no project control system, and an internal rate of return of 12 percent

D. Project D with indirect costs of U.S. $20,000 and 13 resources

为适应你部门的新项目,你需要移动资源从一个项目到另外项目。因为你们部门现在是满负荷。转移资源将不可避免的耽误项目。你应该从下列哪个系哪个项目转移资源引发最小的负面影响?

A.项目A的收益成本率是0.8;没有项目章程,有4个资源;

B.项目B的NPV是60,000美元;12个资源;可变成本每个月在1,000美元到2,000美元之间;

C.项目C的机会成本是300,000美元,没有项目控制系统,内部收益率是12%;

D.项目D的间接成本是20,000美元,13个资源

A

解释:没有项目章程,意味着项目没有正式批准。参考:PMBOK2008 P73。(2009-6-16 14:10:55)


6. You are asked to prepare a budget for completing a project that was started last year and then shelved for six months. All the following would be included in the budget EXCEPT?
A. Fixed costs

B. Sunk costs

C. Direct costs

D. Variable costs

你被要求为某个项目准备预算,该项目去年发起已经被搁置了6个月。下列哪个都会包括在预算内除了:

A.固定成本

B.沉没成本

C.直接成本

D.可变成本

B

解释:沉淀成本,又名沉没成本,是过去花的钱,在作项目决策时不再需要考虑(2009-6-16 14:10:55)


7. The project manager is allocating overall cost estimates to individual activities to establish a baseline for measuring project performance. What process is this?
A. Cost management

B. Cost estimating

C. Determine Budget

D. Cost control

项目经理在将所有成本估算分配到独立的活动上来建立基准用来衡量项目绩效。这是哪个过程?

A.成本管理

B.成本估算

C.制定预算

D.成本控制

C

解释:制定预算是汇总所有单个活动或工作包的估算成本,建立一个经批准的成本基准的过程。参考:PMBOK2008 P174。(2009-6-16 14:10:55)


8.You have just completed the initiating processes of a small project and are moving into the planning processes when a project stakeholder asks you for the project s budget and cost baseline. What should you tell her?
A. The project budget can be found in the project s charter, which has just been completed.

B. The project budget and baseline will not be finalized and accepted until the planning processes are completed.

C. The project management plan will not contain the project s budget and baseline; this is a small project.

D. It is impossible to complete an estimate before the project management plan is created.

你刚刚结束启动过程进入规划过程,此时,某个项目干系人问你项目的预算和成本基线,你应该告诉他什么?

A.项目预算可以在项目章程找到,刚刚完成

B.项目预算和基准直到规划过程完成才能确定

C.项目管理计划不包括项目的预算和基准,因为这是个小项目

D.在项目管理计划完成之前不可能完成估算

B

解释:制定预算是汇总所有单个活动或工作包的估算成本,建立一个经批准的成本基准的过程。制定预算属于规划过程。参考:PMBOK2008 P174(2009-6-16 14:10:55)


9. Your cost forecast shows that you will have a cost overrun at the end of the project. Which of the following should you do?
A. Eliminate risks in estimates and re-estimate.

B. Meet with the sponsor to find out what work can be done sooner.

C. Cut quality.

D. Decrease scope.

你的成本预测显示你将在项目结束成本超支,下列哪个是你应该做的?

A.消除估算的风险,重新估算

B.会见出资人来找出来尽早需要做的事情

C.消减质量

D.减少范围

A

2009-6-16 14:10:55)


10. The seller tells you that your activities have resulted in an increase in their costs. You should:
A. recommend a change to the project costs.

B. have a meeting with management to find out what to do.

C. ask the seller for supporting information.

D. deny any wrongdoing.

卖方告诉你,你的活动将增加他们的成本,你应该:

A.推荐变更项目成本

B.和管理层开会确定需要做什么

C.问卖方支持信息

D.拒绝不道德的行为

C

解释:支持细节 即 估算依据,会显示成本估算的依据、假设、制约因素等。参考:PMBOK2008 P174。(2009-6-16 14:10:55)


11. Your company can accept one of three possible projects. Project A has a net present value (NPV) of U.S. $30,000 and will take six years to complete.Project B has an NPV of U.S. $60,000 and will take three years to complete.Project C has an NPV of U.S. $90,000 and will take four years to complete.Based on this information, which project would you pick?
A. They all have the same value.

B. Project A

C. Project B

D. Project C

你的公司可以接受三个潜在项目中的一个。项目A的净现值(NPV)是30,000美元,需要6年完成;项目B的NPV是60,000美元,需要3年完成;项目C的NPV是90,000美元,需要4年完成,基于这些信息,你会选择哪个项目?

A.它们有同样的价值

B.项目A

C.项目B

D.项目C

D

解释:NPV即净现值,越大越好。(2009-6-16 14:10:55)


12.As a project manager, you are presented with the following information on the net present value (NPV) of several potential projects. Which project is your BEST choice?
A. Project A with an NPV of U.S. $99,000

B. Project B with an NPV of U.S. $120,000

C. Project C with an NPV of U.S. $20,000

D. Project D with an NPV of U.S. -$10, 000

作为项目经理,你展示如下几个潜在项目的净现值(NPV)。哪个项目是你最好的选择?

A.项目A的NPV是99,000美元

B.项目B的NPV是120,000美元

C.项目C的NPV是20,000美元

D.项目D的NPV是-10,000美元

B

解释:NPV (Net Present Value)净现值:按一定的折现率将项目各年净现金流量折现到同一时点的现金累加值。项目的净现值越大越好(2009-6-16 14:10:55)


13. Project A has an internal rate of return (IRR) of 21 percent. Project B has an IRR of 7 percent. Project C has an IRR of 31 percent. Project D has an IRR of 19 percent. Which of these would be the BEST project?
A. Project A

B. Project B

C. Project C

D. Project D

项目A内部收益率(IRR)是21%;项目B的IRR是7%;项目C的IRR是31%;项目D的IRR是19%。下列哪个是最好的项目?

A.项目A

B.项目B

C.项目C

D.项目D

C

解释:内部收益率(IRR)定义:是项目现金流入量现值等于现金流出量现值时折现率。--在项目寿命期内项目内部为收回投资每年的净收益率。内部收益率要大于行业收益率,项目才可以做。对项目而言,IRR越大越好。(2009-6-16 14:10:55)


14. Which of the following represents the estimated value of the work actually accomplished?
A. Earned value (EV)

B. Planned value (PV)

C. Actual cost (AC)

D. Cost variance (CV)

下列哪个展示了实际完成工作的估算价值?

A.实现值(EV)

B.计划值(PV)

C.实际成本(AC)

D.成本偏差(CV)

A

解释:EV,挣值(实现值)指到特定日期已完成工作的预算值。参考:PMBOK2008 P182。(2009-6-16 14:10:55)


15. Value analysis is performed to get:
A. more value from the cost analysis.

B. management to buy into the project.

C. the team to buy into the project.

D. a less costly way of doing the same work.

价值分析的目的是:

A.从成本分析获得更多价值

B.管理层达成项目共识

C.团队对项目达成共识

D.较少的成本完成同样的工作

D

解释:价值分析的定义:以最低的成本识别所要求的功能,为识别的功能确立价值,以最低的成本提供所要求的价值。(2009-6-16 14:10:55)


16. A project manager for a small construction company has a project that was budgeted for U.S. $130,000 over a six week period. According to her schedule, the project should have cost U.S. $60,000 to date. However, it has cost U.S. $90,0oo to date. The project is also behind schedule, because the original estimates were not accurate. Who has the PRIMARY responsibility to solve this problem?
A. Project manager

B. Senior management

C. Project sponsor

D. Manager of the project management office

某个项目经理在小型建筑工作负责某个项目,该项目预算130,000美元,预计花费6周。根据他的进度,项目到今天应该有成本60,000美元。然而实际成本是90,000美元。项目此外还进度拖延,因为最初的估算不准确。谁对解决这个问题负主要责任?

A.项目经理

B.高级管理层

C.项目出资人

D.项目管理办公室的管理者

A

2009-6-16 14:10:55)


17. The ___ can be used to assess outlays and funding requirements
A. Cost assignment matrix

B. Cost baseline

C. Cost variance analysis.

D. Cost control plan

用来评估费用和资金需求的是:

A.成本分配矩阵

B.成本基准

C.成本偏差分析

D.成本控制计划

B

解释:成本绩效基准是经过批准且按时间段分配资金的完工预算,通常用S曲线表示。可以用来评估项目费用的需求。参考:PMBOK2008 P178(2009-6-16 14:10:55)


18. You are project manager for a project with a multi-million value assigned by a company that is listed at a US stock exchange. Recent Earned value analysis after app. 25% completion told you that your project has a CPI of 0.76. What should you do right now?
A. The variance is a signal of a sound project which is well under budget.There is no need for action.

B. A project that much under budget may be a problem for negotiating future budgets. Try to spend money somewhere else.

C. You should immediately inform your management, which should then assess whether this CPI constitutes a material financial issue.

D. It is still early in the project and data are yet inaccurate. Wait a while and allow numbers from the project to stabilize.

你是某个给公司带来数百万价值的项目,这个公司在US股票交易挂牌。最近在完成25%之后实现值分析显示你的项目CPI是0.76。你现在正确的做法是什么?

A.这个偏差代表项目在预算内,不需要采取动作

B.项目在预算内对未来就预算谈判可能是个问题。尝试多花点钱到别的地方

C.你应该立刻通知你的管理层,然后进行评估,不管CPI是不是材料财务问题

D.现在还在项目早期,数据是不准确的。等一段时间,让项目的数据更稳定

C

解释:CPI小于1代表项目成本超支,需要进行评估。参考:PMBOK2008 P183。 (2009-6-16 14:10:55)


19.You are running a project which was budgeted based on some Rough order of magnitude (ROM) estimates with a precision of -50% /+100%. Meanwhile, with new estimates made on detail level and some work already finished, you found out that these estimates were consistently too low and the budget will not be sufficient to successfully run and finish the project. What should you do?
A. You shouldn't worry too much, It is quite normal that early estimates are too optimistic, later estimates are too pessimistic and the project costs will finally settle somewhere in between. So relax!

B. Bring the issue up to your sponsor and discuss how this should be handled. Together with the sponsor adhere to the guidelines which describe how budgets will be reviewed and refined.

C. Try to reduce scope or quality in areas where it cannot create difficulties for you and the team. Finally, it is not your responsibility that an insufficient budget has been created for the project.

D. Find a contractor who can run the project for you. Set the budget as a price limit during the bidding process and accept only Firm fixed price (FFP) offers which do not exceed this price.

你在负责某个项目,该项目的预算基于量级估算,准确范围在一50到+100%之间。其间,当作出新的估算时一些工作已经结束,你发现估算过去一直太低,预算不足以成功运行和结殊项目。你应该做什么?

A.你不应该太担心,这太正常了,早期的估算非常乐观,后期的估算特别悲观,项目的成本将最终落在两者之间。放松点!

B.把这个问题告诉你的发起人,讨论如何解决。和你的发起人一起遵循指南,该指南描述了预算该如何被评估和重新定义

C.尝试减少范围或某些领域的质量,这些领域不会导致你和你的团队出现困难。最后,项目的预算不足这不是你的责任

D.找个承包商,他可以帮助你运行项目。在招标过程设置价格限制在预算之内,只接受固定总价合同,且出价在你的预算之内

B

解释:估算需要重复进行,需要遵循指南。 (2009-6-16 14:10:55)


20. A project underwent a major Scope change, which increased cost and work levels. What does this mean for Earned value data?
A. The cost baseline will be updated and the new baseline will be the basis for future earned value analysis.

B. As baselines should generally not be adjusted, the project is due to exceed its budget from now on.

C. There are several reasons to change a baseline, but not scope changes.The project will exceed its budget.

D. Earned value analysis becomes useless after a scope change, the technique should not be used any more.

项目刚经历了重大的范围变更,导致增加了成本和工作层次。对实现值数据而言意味着什么?

A.项目成本基准将被更新,新的基准将作为未来实现值分析的基础

B.基准应该不被调整,项目将在现在开始超过预算

C.有几个原因需要修改进准,而不是范围变更,项目将超过预算

D.范围变更后实现值分析变得没用,这个技术应该不再使用

A

解释:当项目发生重大变更时,需要重新修订成本基准,作为实现值分析的依据。 (2009-6-16 14:10:55)


21. Post mortem Earned value analysis of a project which is going to be closed showed the following data: SPI: 0.72 CPI: 1.00 What is this telling you?
A. The entire work of the project has been finished ahead of schedule and on budget.

B. The entire work of the project has been finished behind schedule and on budget.

C. The project has been terminated before completion. At that time it was behind schedule and on budget

D. The project has been terminated before completion. At that time it was ahead of schedule and on budget.

某个收尾后的项目最终实现值分析显示如下信息:SPl:0.72;CPI:1.00这告诉你什么?

A.项目的整个工作已经结束,项目进度提前,预算一致

B.项目的整个工作已经结束,项目进度落后,预算一致

C.项目在完成前被终止,此刻进度落后,预算一致

D.项目在完成前被终止,此刻进度提前,预算一致

C

解释:SPI小于1代表进度落后;CPI等于1代表预算一致。因为进度落后所以不可能“项目整个工作已经结束”。参考:PMBOK2008 P183。(2009-6-16 14:10:55)


22. A project manager reported the following Earned value data: PV:$12,400,000;EV: $14,500,000;AC: $14,500,000 What does this mean?
A. The project is over budget and on schedule.

B. The project is under budget and on schedule

C. The project is on budget, but behind schedule.

D. The project is on budget and ahead of schedule.

项目经理报告了如下实现值数据信息:PV:12,400,000美元;EV:14,500,000美元;AC:14,500,000美元。这意味着什么?

A.项目预算超支,进度一致

B.项目预算节约,进度一致

C.项目预算一致,进度落后

D.项目预算一致,进度提前

D

解释:CV=0;SV=2,100,000 代表进度提前,预算一致。参考:PMBOK2008 P182。(2009-6-16 14:10:55)


23.Your project exceeded costs in the past caused by an underestimation of resource costs in the cost baseline: PV: $1,200,000, EV: $1,000,000, AC:$1,200,000 You expect the underestimation to influence the future as much as it did in the past.If the BTC (Budget to complete) is at $1,000,000, what should be your new EAC (Estimate at Completion)?
A. $1,800,000

B. $2,000,000

C. $2,200,000

D. $2,400,000

你的项目成本超支原因是低估了资源的成本:PV:1,200,000美元;EV:1,000,000美元;AC:1,200,000美元,你估计低估的影响在未来还会出现。如果BTC(完工尚需预算)是1,000,000美元,你的新的EAC(完工估算)是多少?

A.$1,800,000

B.$2,000,000

C.$2,200,000

D.$2,400,000

D

解释:如果影响在未来还会出现,表示是典型偏差,使用公式:EAC=BAC/CPI;BAC=BTC+EV,BAC=2百万;所以EAC=2.4百万。参考:PMBOK2008 P184。 (2009-6-16 14:10:55)


24. ___are not necessarily used to establish the Cost baseline of a project?
A. Schedule activity or work package cost estimates

B. The Work breakdown structure and WBS dictionary

C. The Project schedule and Resource calendars.

D. The Risk breakdown structure and the Risk register.

对建立项目成本基准而言什么是不必要的?

A.进度活动或工作包成本估算

B.WBS和WBS字典

C.项目进度和资源日历

D.风险分解结构和风险登记册

D

解释:其他三个选项都是制定预算过程的输入。参考:PMBOK2008 P176。 (2009-6-16 14:10:55)


25. A project was budgeted at $1,000,000. The project is meanwhile being executed,and the following current figures have been assessed: PV: $500,000 EV:$450,000 AC: $550,000 Assuming that the Cost variance was caused by one-time cost drivers, which are no more effective, what Estimate at completion (EaC) can you derive from these figures?
A. $900,000

B. $1,000,000

C. $1,100,000

D. $1,222,222

项目的预算是:1,000,000美元。项目执行期间,收集到如下信息:PV:500,000美元;EV:450.000美元;AC:550,000美元假设成本偏差是一次性原因引发的,以后不会再出现,项目的完工估算(EAC)是多少?

A.$900,000

B.$1,000,000

C.$1,100,000

D.$1,222,222

C

解释:偏差不再出现,使用公式:EAC=AC+BAC-EV=1,100,000。参考:PMBOK2008 P184。(2009-6-16 14:10:55)


26. You are assigned as a project manager for an internal project. During cost planning and budgeting you found out, that there are peak times of costs during the project and other times when costs are fairly low. What could this mean for the project?
A. The fiscal budget mechanism which is used by the performing organization may not allow for cost peaks in your project, and you may have to smooth expenditures over time.

B. You can silently create budget contingencies during low-cost periods and reuse them later during those periods when you have to cover peak levels in project costs.

C. You may find another project manager with a project which has a different rhythm of high and low costs. Then, you may be able to move budget during one project's low cost periods to the other project.

D. You are a project manager and work with a lifecycle budget for your project. Fiscal budgets are a matter of the functional organization, and you have generally not to care about them.

你被分配为某个内部项目的项目经理。当成本规划和预算期间你发现,项目期间某个点成本很高其他实际成本很平稳。这在项目中意味着什么?

A.你们执行组织使用的财政预算机制可能不允许你项目的成本出现高峰,你可能需要平衡费用支出

B.你可以偷偷使用预算应急在低成本期间,在稍后成本较高的时期在重新使用它们

C.你可以找别的项目经理,他们项目的成本曲线有不同的表现,然后,你可能有能力转移一个项目低成本周期到其他项目

D.你是项目经理在你的项目上使用的生命期成本,财政预算是职能组织所关注的,你一般不需要考虑这些

A

解释:一般在项目需要避免某个期间大量成本支出,需要通过资金平衡来实现此目标。参考:PMBOK2008 P178。 (2009-6-16 14:10:55)


27. Your management applies the 10 percent solution: It has requested that you reduce the budget for the project which you are currently initiating by 10%. What will this probably mean for your project?
A. If the budget is cut by 10 percent, then the project will have an accompanying degradation of quality by 10 percent.

B. If the project budget is an honest one, then a reduction in budget must be accompanied by a trade-off in either time or performance.

C. A 10 percent reduction in budget will be accompanied by a loss of performance much less than the target reduction in cost.

D. Most projects have "padded" estimates, and the budgetary reduction will force out the padding from the project.

你的管理层应用了“10%方案”,要求你降低现在启动的项目的成本10%,这对你的项目可能意味着什么?

A.如果预算降低10%,项目的质量将同时降低10%

B.如果项目预算时最刚性的,那么降低预算通常伴随着时间和绩效的均衡

C.当预算降低10%时,通常伴随着绩效的降低不到10%

D.大多数项目有“填充”估算,预算的缩减通常能挤掉项目的“填充”

B

解释:考虑三角形约束,当预算被降低时,需要调整项目的历时和资源投入。 (2009-6-16 14:10:55)


28. During which process is the Cost baseline developed?
A. Integrated change control

B. Cost estimating

C. Schedule development

D. Determine Budget

下列哪个过程完成成本基准?

A.整体变更控制

B.成本估算

C.进度编制

D.制定预算

D

解释:成本基准是制定预算过程的输出。参考:PMBOK2008 P174。 (2009-6-16 14:10:55)


29. If cost variance is negative, but schedule variance is positive, then this indicates:
A. Cost and schedule are not dependent on each other

B. The project is under budget and behind schedule

C.The project is over budget and ahead of schedule

D.Crashing may be recommended to make the cost variance positive

如果成本偏差是负的,进度偏差是正的,这意味着:

A.成本和进度没有相互依赖关系

B.项目在预算之内进度滞后

C.项目预算超支进度提前

D.赶工可能被推荐来使成本偏差为正

C

2009-6-16 14:10:55)


30. Project setup costs are an example of:
A. variable costs.

B. fixed costs.

C. overhead costs.

D. opportunity costs.

项目准备成本是什么成本的例子?

A.可变成本

B.固定成本

C.间接成本

D.机会成本

B

解释:固定成本不会因为产品数量而改变。(2009-6-16 14:10:55)


31. Which factor would NOT be considered when choosing between two projects to undertake?
A. Net present value (NPV)

B. Benefit cost ratio (BCR)

C. Payback period

D. Law of diminishing returns

下列哪个不需要考虑在两个项目中做出选择时:

A.净现值(NPV)

B.收益成本率(BCR)

C.回收期

D.收益递减法则

D

解释:选项D不是项目选择指标。(2009-6-16 14:10:55)


32. How close to actual costs should a definitive budget estimate be?
A. -75 percent to +25 percent

B. -10 percent to +15 percent

C. +10 percent to -25 percent

D. -5 percent to +10 percent

确定的预算估算和实际成本接近范围是:

A.-75%到+25%

B.-10%到15%

C.+10到-25%

D.-5%到10%

B

解释:预算估算的等级是-10%——+15%。参考:PMBOK2008 P168。 (2009-6-16 14:10:55)


33. Which of the following is an example of a parametric estimate?
A. Dollars per module

B. Learning bend

C. Bottom-up

D. CPM

下列哪个是参数估算的例子?

A.每个模块多少美元

B.学习曲线

C.自下而上

D.CPM

A

解释:参数估算根据某个参数(如每平米价格)来估算项目活动所需费用。参考:PMBOK2008 P172。(2009-6-16 14:10:55)


34. A schedule performance index (SPI) of 0.76 means:
A. you are over budget.

B. you are ahead of schedule.

C. you are only progressing at 76 percent of the rate originally planned.

D. you are only progressing at 24 percent of the rate originally planned.

进度绩效指数(SPI)等于0.76意味着:

A.你的预算超支

B.你的进度提前

C.你的进度完成了最初计划的76%

D.你的进度完成了最初计划的24%

C

解释:SPI=EV/PV;EV是实际完成工作;PV是计划完成工作。参考:PMBOK2008 P183。(2009-6-16 14:10:55)


35. The main focus of life cycle costing is to:
A. estimate installation costs.

B. estimate the cost of operations and maintenance.

C. consider installation costs when planning the project costs.

D. consider operations and maintenance costs in making project decisions.

生命期成本主要考虑:

A.估算安装成本

B.估算运营和维护成本

C.在规划项目成本时考虑安装成本

D.在做出项目决策时考虑运营和维护成本

D

解释:生命周期成本就是产品生命周期成本,包括项目本身的成本和项目成果(产品)在使用中的运营和维护成本。参考:PMBOK2008 P167。(2009-6-16 14:10:55)


36. The cost of choosing one project and giving up another is called:
A. fixed cost.

B. sunk cost.

C. net present value (NPV).

D. opportunity cost.

选择一个项目放弃另一个项目的成本叫:

A.固定成本

B.沉没成本

C.净现值

D.机会成本

D

解释:请理解机会成本的概念:选择另一个机会而所放弃的某个机会的收益。如卖白菜可以赚1000元,写程序可以赚10000,如果选择卖白菜,而不能去写程序,那么说明卖白菜的机会成本为10000元。(2009-6-16 14:10:55)


37. Double declining balance is a form of:
A. decelerated depreciation.

B. straight line depreciation.

C. accelerated depreciation.

D. life cycle costing.

双倍余额递减法是:

A.减速折旧

B.直线折旧

C.加速折旧

D.生命期成本

C

解释:双倍余额法是加速折旧法的一种形式。折旧越快,交税越少。(2009-6-16 14:10:55)


38. If earned value (EV) = 350, actual cost (AC) = 400, planned value (PV) =325, what is cost variance (CV)?
A. 350

B. -75

C. 400

D. -50

如果EV=350,AC=400,PV=325,CV是多少?

A.350

B.-75

C.400

D.-50

D

解释:CV=EV-AC=-50。(2009-6-16 14:10:55)


39. Which of the following techniques uses statistical relationship between historical data and other variables to calculate a cost estimate for a schedule activity resource?
A. Activity Cost Estimating

B. Parametric Estimating

C. Bottom Up Estimating

D. Analogous Estimating

下列哪个技术使用历史数据之间的统计关系和其他变量来计算每个进度活动所需资源的成本?

A.活动成本估算

B.参数估算

C.自下而上估算

D.类比估算

B

解释:参数估算根据某个参数(如每平米价格)来估算项目活动所需费用。参考:PMBOK2008 P172。(2009-6-16 14:10:55)


40. In which project management process group is the detailed project budget created?
A. Initiating

B. Before the project management process

C. Planning

D. Executing

详细的项目预算是在哪个项目管理过程组中完成的?

A.启动

B.在项目管理过程组织之前

C.规划

D.执行

C

解释:项目预算在规划过程中完成。参考:PMBOK2008 P178。(2009-6-16 14:10:55)


41. In your project, you are using project files, records and closed contracts to determine the cost of many categories of resources. This will help you to estimate the cost of the resources needed to complete the project activities. This information is available to you as a part of :
A. Chart of accounts

B. Historical information

C. Activity duration estimates

D. Estimating publications

在你的项目中,你在使用项目档案,记录和收尾的合同来确定不同资源类别的成本。这将帮助你来估算完成项目活动所需要的资源的成本。这些信息是可以利用的对你而言作为下列的一部分:

A.账目表

B.历史信息

C.活动历时估算

D.估算出版物

B

解释:历史信息属于组织过程资产的一部分,作为成本估算的输入。参考:PMBOK2008 P171。(2009-6-16 14:10:55)


42. Which type of costing is team training?
A.Direct

B.NPV

C.Indirect

D.Fixed

团队培训属于哪个类型的成本?

A.直接成本

B.NPV

C.间接成本

D.固定成本

C

解释:培训的效果可以用到多个项目上,因此培训费用属于间接成本。 (2009-6-16 14:10:55)


43. Your project exceeded costs in the past caused by an underestimation of resource costs in the cost baseline: PV: $1,200,000, EV: $1,000,000,AC:$1,200,000 You expect the underestimation to influence the future as much as it did in the past. If the BTC (Budget to complete) is at $1,000,000, what should be your new EAC (Estimate at Completion)?
A.$1,800,000

B.$2,000,000

C.$2,200,000

D.$2,400,000

你的项目成本超出了基准,原因是在基准对资源的成本估算错误。PV:1,200,000;EV:1,000,000;AC:1,200,000;你估计错误的估算未来还将出现。如果BTC是1,000,000;你新的EAC是?

A.$1,800,000

B.$2,000,000

C.$2,200,000

D.$2,400,000

D

解释:未来还出现表明典型偏差,EAC=BAC/CPI=2百万除5/6=2.4百万。(2009-6-16 14:10:55)


44.1f you have Estimate at Completion(EAC) and Budget at Completion(BAC),How will you compute Cost Performance Index(CPI)?
A.Divide BAC by EAC

B.Divide EAC by BAC

C.Multiply BAC and EAC

D.Cannot be calculated with the given data

如果你知道EAC(完工估算)和BAC(完工预算),你如何计算CPI(成本绩效指数)?

A.BAC除以EAC

B.EAC处于BAC

C.BAC乘以EAC

D.不能根据上述数据计算

A

解释:因为 EAC=BAC/CPI;所以,CPI=BAC/EAC(2009-6-16 14:10:55)


45. You are arranging a big company get together and you are expecting 1000 participants. You have rented a large hall and due to heavy rain only 800 people turned up for the event You have spent $1,000 for the hall. Which of the following is true?
A.$800 is direct cost and $200 is indirect cost

B.$800 is fixed cost and $200 is variable cost

C.$1000 is Fixed cost

D.$800 is variable cost and $200 is fixed cost

你负责一个大型公司的聚会活动,你预期有1000多人会参加。你租借了巨大的礼堂,由于大雨只有800人到场参加此活动。你为礼堂花费了1000美元。下列哪个是正确的?

A.800美元是直接成本,200美元是间接成本

B.800美元是固定成本,200美元是可变成本

C.1,000美元是固定成本

D.800美元是可变成本,200美元是固定成本

C

解释:租借场地的费用不会因为参加的人数而改变,所以是固定成本。(2009-6-16 14:10:55)


46. You are talking to the project manager of Alpha Networks. He was talking about his prestigeous project Starnet which he executed last year and said the payback period is ended. What do you understand from this?
A.Starnet project has achieved its maximum profit projections

B.The monthly revenue of Starnet project is above month!y operation cost

C.Cumulative Revenue and cumulative cost from Starnet became equal.

D.Unit profit is realized for Starnet project

你在和Alpha网络的项目经理交流。他说他的项目Starnet已经在去年结StarnetStarnet知道回收期是指?

A.Starnet项目已经实现了最大利润

B.Starnet项目的每月收入已经超过其每月运营的成本

C.Starnet项目的累积成本和累计收入已经相等

D.Starnet项目的单位利润已经实现

C

解释:回收期就是某个项目的成本全部收回所需的时间,从第一天投入成本开始到所有成本收回之日。 (2009-6-16 14:10:55)


47. You are performing Earned value technique on your project. After budget approval, an additional and unexpected cost item has been identified, which made the project more expensive some weeks ago. The item has meanwhile been paid by the project team, and it is expected that for the remaining duration of the project, costs will be as budgeted. In this case, which is the best formula to calculate EAC (Estimate at Completion)?
A. EaC = BaC- CV

B. EaC = BaC / CPI

C. EaC = AC + BtC / CV

D. You can not compute the EaC.

你在使用EVT技术在你的项目上。在预算批准后,一个额外的和未被预期的成本条目被识别,这导致项目花费了比以前几周更多的资金。这个成本条目已经被支付,针对项目剩下的历时已经为此成本条目准备了预算。在这种情形下,下列哪个是计算EAC的最好公式?

A.EAC=BAC.CV

B.EAC=BAC,CPI

C.EAC=AC+BTC,CV

D.你不能计算EAC

A

解释:因为未被识别的成本条目所引发的偏差,今后不再出现,属于非典型偏差;所以使用公式EAC=AC+BAC-EV=BAC-CV。(2009-6-16 14:10:55)


48. An organization is considering a project opinion which will cost $100,000 and take 6 months to deliver. It is forseen that benifits will start being delivered at month 7 providing $ 20,000 per month. What is the payback period?
A. Information is insufficient

B. 11 months

C. 5 months

D. 6 months

一个组织正在考虑一个项目方案,这个项目将耗资$100,000,用6个月交付。他们预测项目将从第7个月开始赢利,而后每个月赢利$20,000。项目的回收期是多长时间?

A.信息不足

B.11个月

C.5个月

D.6个月

B

解释:回收期计算:一个月收回2万,5个月收回所有投资10万。 (2009-6-16 14:10:55)


49.Continually measuring and monitoring the actual cost versus the budget is done to
A. analyze the reasons for variances.

B. establish the variances

C. identify the problems

D. All of the above.

连续地测量和监视实际发生的费用,并与预算比较的目的是

A.分析偏差的原因

B.确定偏差

C.识别问题

D.上述都是

D

2009-6-16 14:10:55)


50. Which type of cost estimate is based on individual activities?
A. Top-down

B. Bottom-up

C. Parametric

D. Analogous

下列哪种费用估算方法是基于单个活动的?

A.自上而下

B.自下而上

C.参数法

D.类比法

B

解释:自下而上估算,首先需要估算每个活动所需费用。参考:PMBOK2008 P172。(2009-6-16 14:10:55)