ITIL foundations 争议题目讨论
2008-04-30 13:44
239 查看
1. What information is not required to set up a process
a. the process owner
b. the trigger(input)
c. the objective
d. the desired results(outputs)
教材定义说里说 A process is a bundle of logical activities combined to achieve a certain goal(result).
又提到
For every process inputs and outputs are definded.
排除 b,d
It is important, therefore, that each process should have an owner.
似乎可以排除a.但是 ITIL 给出的process 定义图里面又明明给出了objective。
到底选哪个呢?
2. What is the meaning of the term Serviceability ?
Serviceability 是availability management 中的一个概念. 考量的是服务出现问题时, 可以获得外部供应商的支持的能力. 与之相关的就是 underpinning contract.
3. The Capacity Manager asks the user of an application whether a certain activity can be performed at night so that the CPU is not overloaded during the day.
What part of the Capacity process does this refer to ?
a. Application Sizing
b. Modeling
c. Application Management
d. Demand Management
Application Sizing: forecasts (hardware) resources for new applications. 针对对新应用的.在项目开始阶段
Demand Management: The objective of influencing demand and the use of resources. 针对现有系统的优化.影响或者更改使用计划.
The Capacity Plan: 考量现有的resouce utilization and service performance, 比对业务发展计划,为将来的IT Service制定resource需求规划.
选 D.
a. the process owner
b. the trigger(input)
c. the objective
d. the desired results(outputs)
教材定义说里说 A process is a bundle of logical activities combined to achieve a certain goal(result).
又提到
For every process inputs and outputs are definded.
排除 b,d
It is important, therefore, that each process should have an owner.
似乎可以排除a.但是 ITIL 给出的process 定义图里面又明明给出了objective。
到底选哪个呢?
2. What is the meaning of the term Serviceability ?
Serviceability 是availability management 中的一个概念. 考量的是服务出现问题时, 可以获得外部供应商的支持的能力. 与之相关的就是 underpinning contract.
3. The Capacity Manager asks the user of an application whether a certain activity can be performed at night so that the CPU is not overloaded during the day.
What part of the Capacity process does this refer to ?
a. Application Sizing
b. Modeling
c. Application Management
d. Demand Management
Application Sizing: forecasts (hardware) resources for new applications. 针对对新应用的.在项目开始阶段
Demand Management: The objective of influencing demand and the use of resources. 针对现有系统的优化.影响或者更改使用计划.
The Capacity Plan: 考量现有的resouce utilization and service performance, 比对业务发展计划,为将来的IT Service制定resource需求规划.
选 D.
相关文章推荐
- 树分治&树链剖分相关题目讨论
- 讨论题目
- C/C++面试常考题目讨论之二:如何通过函数来分配空间
- CodeForces 589D --- D. Boulevard (数学题目--枚举分类讨论)
- 就题目的再次讨论--AFei来报道
- 一道C语言题目引发的讨论
- 20070926日下午工作流与ITILQQ群 事件管理 讨论聊天记录
- 中国的ITIL落地之路 转至ITIL先锋论坛讨论
- 讨论区:一个数学方差题目
- Google, Facebook算法题目和其他资料的讨论blog
- 兴趣讨论:从一道技术面试题目说起
- 一道程序初始化顺序题目引起的讨论
- ITSM & ITIL QQ群 2月28日讨论 ITIL中什么最重要和优先级最高的聊天记录和总结
- 20070926日下午工作流与ITILQQ群 事件管理 讨论聊天记录
- 2011微软暑期实习笔试海选题目(欢迎讨论)
- 组讨论的经典面试题目
- 针对那道ABCDEF的题目大家反映比较大,单独拿出来讨论一下
- ITIL群讨论ITIL相关内容
- 一道简单的ACM题目讨论
- CSDN论坛争议帖:"C++读写锁"引发一场揪出伪专家的讨论